UGL – Defence
UGL – Defence
Project Scope:
PGSR was engaged to provide all trades and non-trades resources to execute the 10 yearly tank inspections of the QCI Tanks.
Specific Works included;
-
- Internal & External Inspection
- Removal & Replacement of Safety Valves
- Testing of Safety Valves
- Mechanical Works
Customer Details:
UGL / Defence
Project Duration:
3 weeks – 70hrs/week
Resources provided:
Average 3 – 658 man-hours in total
Tooling provided:
Valve Testing Equipment and Tooling — fully equipped for self-performance