UGL – Defence

UGL – Defence

Project Scope:

PGSR was engaged to provide all trades and non-trades resources to execute the 10 yearly tank inspections of the QCI Tanks.

Specific Works included;

    • Internal & External Inspection
    • Removal & Replacement of Safety Valves
    • Testing of Safety Valves
    • Mechanical Works

Customer Details:
UGL / Defence

Project Duration:
3 weeks – 70hrs/week

Resources provided:
Average 3 – 658 man-hours in total

Tooling provided:
Valve Testing Equipment and Tooling — fully equipped for self-performance