Project Scope:

PGSR was engaged to provide all trades and non-trades resources to execute the major outage works on the Opal Unit 6 Boiler and Associated Plant.

Specific Works included;

    • Internal & External Scaffolding
    • Insulation Removal & Replacement
    • Boiler Survey
    • Non Destructive Testing
    • Phased Array Ultrasonic Testing
    • Pressure Welding – AS4041
    • Removal & Replacement of Safety Valves
    • Mechanical Fan Works

Customer Details:
Opal Australian Paper, Maryvale Paper Mill

Project Duration:
6 weeks – 70hrs/week

Resources provided:
Average 75 – 17,625 man-hours in total

Tooling provided:
Four tooling containers — fully equipped for self-performance