Opal Australian Paper, Maryvale Paper Mill
Opal Australian Paper, Maryvale Paper Mill
Project Scope:
PGSR was engaged to provide all trades and non-trades resources to execute the major outage works on the Opal Unit 6 Boiler and Associated Plant.
Specific Works included;
-
- Internal & External Scaffolding
- Insulation Removal & Replacement
- Boiler Survey
- Non Destructive Testing
- Phased Array Ultrasonic Testing
- Pressure Welding – AS4041
- Removal & Replacement of Safety Valves
- Mechanical Fan Works
Customer Details:
Opal Australian Paper, Maryvale Paper Mill
Project Duration:
6 weeks – 70hrs/week
Resources provided:
Average 75 – 17,625 man-hours in total
Tooling provided:
Four tooling containers — fully equipped for self-performance